Late April saw the placement of 18 pre-stressed concrete planks to the bridge separating Coombs 1 Residential Estate from the adjacent (complete) Stage 2. The Cardno designed bridge spans a future trunk pedestrian/cyclepath route and major overland flow stormwater. The skew of the bridge abutments in all three planes meant precision construction was required. The relative ease of installation of the planks in this instance says alot about the hard work and precision of the site engineering team and concrete subcontractors.